CMAL and SSEN have started infrastructure works at Port Askaig to provide shore power for the new Islay vessels. The project is being delivered in collaboration with Argyll and Bute Council and CalMac.
The scheme includes installation of a new high-voltage cable from the SSE substation at Keills to Port Askaig pier.
The full programme is expected to take four to five months. Travellers using Port Askaig are advised to allow extra time and expect delays during the construction period.