September 22, 2022
- Metsä Board will start pre-engineering for a new folding boxboard mill with an annual capacity of approximately 800,000 tonnes at the Kaskinen mill site in Finland.
- The pre-engineering phase will include technical design, design of infrastructure and logistics solutions and tendering for the main equipment. As part of the pre-engineering, an environmental impact assessment and an environmental permit process will be launched.
- The company estimates that a possible investment decision could be made in 2024 at the earliest.