The E-ferry project has seen some delays. It encountered challenges with the interconnection of different systems, which required more time than planned.
The project partners initially expected that the commissioning would take 10 weeks and last from December to mid-February. After that, berthing- and sea trials were going to take place. The delivery to Ærø Færgerne was planned for the middle of March.
Now the final testing will take place at the end of April.
Handing over to Ærø Færgerne is planed for 3 May.
After crew training the public service will start in mid June.