IN THE MEDIA

By | 2019 newsletter week 19 | No Comments

Ferguson’s Bosses Welcome an Investigation into The Future of Shipyard – And Insist That Business Is Booming

Ferguson’s bosses have welcomed an investigation into a delayed £97m ferry contract and the future of yard – and insist that business is booming.

Company chief executive Gerry Marshall has broken his silence after a senior Scottish Government minister confirmed a further setback in the delivery of the two new CalMac vessels which are under construction at the Newark site.

GLEN SANNOX is now 14 months late. Hull 802 is around 20 months behind schedule.

Ferguson’s and CMAL are in dispute over the extent of changes made to the design of the ships.