The project includes the construction of a new quay wall at Berth 52 East and a significant new RoRo facility at Berth 53 to support growing freight and ferry traffic and introducing new technology for the safer berthing of ever larger vessels.
The works involve the installation of a combi-wall quay structure, a double-tier linkspan and modern bridge system for RoRo vessels, and extensive marine and landside infrastructure. Berth 53 will feature a 290-metre open jetty with nine marine platforms (known in the industry as Dolphins), while the landside development includes a 400m access road, electrical services, CCTV, and an asphalt-paved operational yard.