Ferguson Marine (Port Glasgow) has completed another significant milestone in the dual fuel ferry project with the installation of the bulbous bow on Hull 802.

 

In recent weeks, three stern units have been lifted into place on Hull 802.  When finished, these units will house the steering gear and other equipment and will support the car deck and stern ramp.

Earlier this year, structural work on first vessel GLEN SANNOX was completed following the installation of a reworked funnel and newly constructed mast, as well as completion of the structure around the stern and inside the hull.

GLEN SANNOX is scheduled to be delivered between July 2022 and September 2022.

Hull 802 is scheduled to be delivered between April 2023 and July 2023.