- In a letter to the Scottish Parliament’s Net Zero, Energy & Transport Committee, Ferguson Marine CEO Graeme Thomson confirms progress on GLEN ROSA.
- Key milestones include removal of funnels (20 May), silencer installation (from 24 June), and dry dock scope finalisation with Dales Marine (for 17 July).
- LNG-related upgrades and galley equipment installation (24 September) are also scheduled.
- Delivery remains on track for Q2 2026, with a forecast cost of £172.5 million and £12.5 million risk contingency.
- A site visit for the Committee is planned for 19 September 2025.