All Hands On Deck For HONFLEUR
As part of the process to reorganise the Flensburg-based shipyard, FSG has been in negotiations with customers and suppliers since the beginning of the year. Several measures have been implemented in order to successfully achieve this target.
The ro-pax ferry for Brittany Ferries is in the process of intensive outfitting. For optimal progress of this vessel –HONFLEUR–, it was necessary to postpone the start of the production of newbuilding no. 781, the eighth ro-ro vessel for Siem.
This has led to a partial and temporary underemployment in one part of the production. For this reason, the Company’s management and Works Council have agreed to apply to the Labour Employment Agency for short-time work in this area.
The application has already been submitted. The effects on the affected area are being kept to a minimum. The majority of the affected employees will be able to bridge this period either by reducing overtime hours previously worked or will be temporarily employed in other areas of production.